Engineering, Procurement and Construction Agreement (EPC Agreement)
Contract Template for New Zealand

New Zealand EPC agreement for a commercial facility with engineering integration, procurement, statutory payment procedures, commissioning and performance guarantees.

Governing law: New ZealandPublished templateUpdated 2026-10-09
ENGINEERING, PROCUREMENT AND CONSTRUCTION AGREEMENT (EPC AGREEMENT)
# ENGINEERING PROCUREMENT AND CONSTRUCTION AGREEMENT *New Zealand* Date: [date]. Owner: [full legal name, constitution, NZBN/company number and address] (Owner). EPC Contractor: [full legal name, constitution, NZBN/company number and address] (Contractor). The Facility is [industrial/infrastructure facility] at [address] (Site). The EPC Works are the engineering, procurement, construction, commissioning and handover described in Schedule 1. Contract Price means NZD [amount] plus GST, adjusted only under this Agreement. Scheduled Completion Date means [date]. Taking Over has the meaning in clause 8. Variation means a change authorised under clause 6. Working Day has the meaning given in the Construction Contracts Act 2002. ## 1. EPC delivery The Contractor must engineer, procure, construct, test, commission and hand over the Facility in accordance with the output specifications, capacity, efficiency and performance guarantees in Schedule 1, the consented documents, the New Zealand Building Code and other applicable law. It must provide all labour, supervision, equipment, materials, temporary works and services allocated to it. The Contractor is responsible for integration of the EPC Works and coordination of designers, vendors and subcontractors. It must promptly notify an error, ambiguity, unsafe requirement or missing interface that a competent EPC contractor should identify. It may rely on Owner information expressly listed as a reliance item in Schedule 1 but must verify Site data and dimensions reasonably capable of verification. ## 2. Engineering, quality and records The Contractor must prepare the calculations, drawings, specifications, software configurations, quality plans, vendor data and operating documents required by Schedule 1. Owner or Engineer review is only for conformity with stated requirements and does not transfer responsibility, authorise a deviation or amend this Agreement. The Contractor must maintain a controlled document register and deliver final as-built documents, producer statements, warranties, test records, spares lists, manuals and training materials at handover. ## 3. Consents, Site and safety The Owner must provide lawful Site access, authority to construct and operate, Owner consents and inputs by the dates in Schedule 1. Schedule 1 must allocate building consent, resource consent, utility approvals, inspections, code compliance certification and operating approvals. The responsible party must obtain each approval before the affected activity. Each party must comply with duties under the Health and Safety at Work Act 2015 and consult, co-operate and co-ordinate with other duty holders. The Contractor controls its methods and workforce, maintains competent supervision and Site records, and protects the Site and adjoining property. No term transfers or limits a statutory duty. ## 4. Payment claims and retentions The Contractor may serve payment claims under section 20 of the Construction Contracts Act 2002 at the valuation dates or milestones in Schedule 2. Each claim must identify the relevant period and EPC Works, calculate the amount, state the due date and include the prescribed explanation. Within [10] Working Days after service, the Owner must pay the claimed amount or serve a payment schedule complying with section 21 that states the scheduled amount and reasons for each difference. Payment is due [20] Working Days after service unless Schedule 2 lawfully states another date. Statutory debt, suspension and adjudication rights remain available. Any retention must be stated in Schedule 2. Where subpart 2A of the Construction Contracts Act 2002 applies, retention money is trust money and the retaining party must keep, use, account for, report on and pay it only as that Act permits. Release conditions cannot override mandatory law. ## 5. Procurement, title and security The Contractor must procure compliant equipment and materials from qualified sources, conduct the inspections in Schedule 1 and provide certificates and warranties. It must not substitute a material item without a Variation. Title passes on payment or delivery to the Site, whichever occurs first, free of undisclosed security interests. Risk and care remain with the Contractor until Taking Over except to the extent caused by the Owner. Any advance-payment bond, performance bond or warranty security must be stated in Schedule 2, including form, amount, reduction, release and expiry. A call may be made only consistently with its terms and applicable law. ## 6. Variations A Variation is effective only when a written instruction or agreement states the changed requirement, valuation method, programme effect, performance-guarantee effect and revised Scheduled Completion Date. If price is not agreed before work proceeds, it is determined using Schedule 2 rates or, if none, reasonable verified cost plus [percentage]% overhead and profit. Urgent protective work may proceed with prompt notice and records. ## 7. Programme and delay The Contractor must maintain a programme showing engineering, long-lead procurement, construction, pre-commissioning, performance testing and handover. It must notify a delaying event within [three] Working Days after awareness and provide particulars and mitigation within [seven] further Working Days. The Scheduled Completion Date extends to the extent completion is delayed by an approved Variation, Owner default, late access or input, an undisclosed physical condition not reasonably discoverable before signing, or an unavoidable event beyond reasonable control despite mitigation. Delay damages in Schedule 2 apply only to Contractor-caused delay after that date, at the stated daily amount and cap, subject to the law on penalties. ## 8. Commissioning and Taking Over The Contractor must conduct factory, Site, commissioning, reliability and performance tests in Schedule 1 and give reasonable notice. Taking Over occurs when the Facility passes the required tests, is safe and ready for intended operation, required Contractor approvals have been obtained, agreed training is complete, essential manuals and spares are delivered, and only minor items not preventing operation remain. Within [five] Working Days after a Taking Over request, the Owner must issue a Taking Over Certificate or a reasonable list of material failures. A performance result below a guaranteed value but at or above the minimum acceptance level may be accepted only with the adjustment in Schedule 2. A result below the minimum level requires correction or a signed Variation. The Contractor must correct notified defects caused by its breach within a reasonable time during the [twelve]-month Defects Period. Taking Over, operation or final payment does not waive latent defects, fraud or mandatory rights. ## 9. Intellectual property, insurance and liability The Contractor retains intellectual property in its engineering documents but grants the Owner a perpetual, royalty-free, transferable licence to use and adapt them to complete, operate, maintain, repair and alter the Facility. It must have authority to grant that licence. Before mobilisation, the Contractor must provide evidence of the professional indemnity, transit, contract works, public liability and other insurance in Schedule 3. Each party is liable for direct loss caused by breach, negligence or wilful misconduct. No cap excludes fraud, death or personal injury caused by negligence, unpaid amounts or liability that cannot lawfully be limited. Any cap is stated in Schedule 3. ## 10. Suspension, termination and disputes A party may suspend affected performance after [seven] Working Days' notice of an uncured material breach; immediate suspension is permitted for imminent safety risk. Statutory suspension rights remain available. A party may terminate for a material breach remaining uncured [fifteen] Working Days after notice or insolvency, subject to mandatory law. On termination, the Contractor must make the Site safe and hand over paid-for work, equipment and records; the Owner must pay for conforming work and reasonable demobilisation, less lawful set-off and reasonable completion cost caused by Contractor default. Representatives must meet within [five] Working Days after a dispute notice. Either party may refer a dispute to adjudication under the Construction Contracts Act 2002 at any time. Other statutory or court remedies remain available. New Zealand law governs and its courts have jurisdiction. The Contractor remains responsible for subcontractors and may not subcontract the whole EPC Works without consent. Amendments must be signed. Notices must be written and served consistently with statutory requirements and Schedule 3. Counterparts and electronic signatures may be used where the Contract and Commercial Law Act 2017 permits. ## SCHEDULE 1 — FACILITY AND TECHNICAL REQUIREMENTS Site, Facility, battery limits, exclusions and reliance items: [details]. Output specifications and guaranteed performance: [details]. Minimum acceptance levels and test methods: [details]. Engineering documents, review periods and quality plan: [details]. Programme, long-lead items and Scheduled Completion Date: [details]. Consents, inspections and responsible party: [details]. Commissioning, training, spares and handover records: [details]. ## SCHEDULE 2 — PRICE, CLAIMS AND SECURITIES Contract Price and GST: [details]. Claim intervals, calculations and evidence: [details]. Payment-schedule period and due date: [details]. Advances, retentions and securities: [details or none]. Variation rates and overhead/profit percentage: [details]. Delay damages and performance adjustments: [details]. ## SCHEDULE 3 — INSURANCE, LIABILITY AND CONTACTS Policies, limits and periods: [details]. Liability cap, if agreed: [details]. Authorised representatives and notices: [details]. ## SIGNATURES For the Owner: [authorised signatory, position, signature and date]. For the Contractor: [authorised signatory, position, signature and date].

Licensed under CC BY 4.0. Attribution is required when you publish or redistribute this Template or an adapted version to the public. Attribution is not required merely because you use or adapt the Template for your own business or legal purposes, including preparing, negotiating, signing, or exchanging an agreement with a counterparty. License details.