Construction Joint Check Agreement
Maine, United States

[Prime contractor legal name and address] (Contractor)
[Subcontractor legal name and address] (Subcontractor)
[Supplier legal name and address] (Supplier)

1. Covered payment
This agreement covers one payment for [project and address], a privately funded commercial project in Maine owned by [owner legal name]. USD [amount] (Covered Amount) is due from Contractor to Subcontractor under [subcontract and invoice or payment application reference] and from Subcontractor to Supplier for project materials under [supply contract or purchase order and invoice reference]. Subcontractor directs Contractor to pay that amount by joint check for credit under section 3.

2. Issue and endorsement
Contractor will deliver an uncertified check by [date] to Subcontractor, with a copy to Supplier. The check must be payable to “[Subcontractor legal name] and [Supplier legal name]” for the Covered Amount. Subcontractor will promptly endorse and deliver it to Supplier. Supplier will promptly endorse and deposit it into Supplier's account. Each payee must use its own authorized signer. Both endorsements are required.

3. Final collection
Taking the check suspends neither debt. On final payment by the bank and receipt of collected funds by Supplier, Supplier will credit the specified supplier invoice, and Contractor and Subcontractor will apply the same credit to the specified subcontract payment. Supplier will promptly confirm the check number, collection date and credit in writing. Issuance, endorsement and provisional credit do not establish payment. If the check is lost, rejected, dishonored or reversed, the party learning of it will promptly notify the others. The parties will correct credits and cooperate to pay any balance still due without duplicate collection.

4. Rights and deadlines
The check or remittance must identify the section 1 allocation. The payees will return without deposit any check conditioned on settlement or release. Except for collected credits under section 3, this agreement and the check preserve claims, liens, bond rights, statutory notices, retainage and payment deadlines. The parties will use another lawful payment method if needed to meet a deadline. No party guarantees another's debt. Maine law governs. This agreement takes effect on the last signature date.

Contractor [authorized signature, name and title]. Date [date].
Subcontractor [authorized signature, name and title]. Date [date].
Supplier [authorized signature, name and title]. Date [date].


---
License: Licensed under CC BY 4.0. Attribution is required when you publish or redistribute this Template or an adapted version to the public. Attribution is not required merely because you use or adapt the Template for your own business or legal purposes, including preparing, negotiating, signing, or exchanging an agreement with a counterparty. License details.
License details: https://contract-templates.getfebruary.ai/license/