CONSTRUCTION CHANGE ORDER AGREEMENT

Hawaii, US

Change order number: [number]
Effective date: [date]

Owner: [full legal name and entity type], of [address] (Owner).
Contractor: [full legal name and entity type], Hawaii contractor license number [number], of [address] (Contractor).

Base contract: the written construction contract dated [date] for the private commercial project at [address] (Base Contract).

1. Limited modification

The parties modify only the Base Contract items expressly stated in this Change Order. All other terms remain unchanged. This form is for private commercial construction. It is not a residential home construction or home improvement contract, a public procurement change order, a design-professional engagement, or a substitute for any disclosure, bond, procurement, or licensing document required for those transactions.

2. Changed work

Contractor shall add, delete, or revise the following work (Changed Work): [precise description, drawings, specifications, quantities, locations, materials, and exclusions]. The following dated documents are incorporated solely for the Changed Work: [list]. If they conflict, this signed Change Order controls, followed by [priority].

The Changed Work excludes [list]. An allowance of $[amount] covers only [item]; any unused balance reduces the Contract Sum and any excess requires another signed change. Owner shall provide by [date]: [access, decision, utility shutdown, owner-supplied item, or other dependency].

3. Price adjustment

The Contract Sum is [increased/decreased] by $[amount], changing it from $[old amount] to $[new amount]. This adjustment includes Contractor's labor, materials, equipment, supervision, overhead, profit, taxes, and subcontractor costs for the Changed Work except: [stated exclusion]. Payment is due under the Base Contract's progress-payment procedure upon completion of these milestones: [milestones].

No estimate, proposal, field conversation, daily report, or unsigned directive changes the Contract Sum. If concealed conditions or a required authority directive materially changes the described work, Contractor shall stop the affected portion when safe and request a written change with supporting cost and time information.

4. Schedule adjustment

The Contract Time is [increased/decreased/not changed] by [number] calendar days. The revised substantial-completion date is [date]. The adjustment accounts for [identified effect]. Contractor shall promptly notify Owner of an excusable delay affecting the Changed Work and use reasonable efforts to mitigate it. This Change Order resolves only the time impacts expressly identified here and [does/does not] waive previously submitted claims listed in [document].

5. Authorization and performance

Contractor shall not begin Changed Work until both parties sign, applicable permits or approvals are obtained, and Owner gives any notice to proceed required below. In an emergency threatening persons or property, Contractor may perform only reasonable protective work after prompt notice and shall document the circumstances and cost; further work requires written authorization.

Contractor represents that its listed Hawaii license is active and covers the work it performs or supervises. Contractor remains responsible for construction means, methods, sequencing, site safety, qualified personnel, permits assigned to it, and subcontractor compliance. Owner remains responsible for permits and approvals assigned to Owner under the Base Contract. Neither party authorizes unlicensed contracting or professional design.

6. Quality, inspection, and closeout

Changed Work must comply with the Base Contract, incorporated documents, applicable permits, manufacturer instructions, and law. Inspection or payment does not waive a latent defect. Contractor shall correct nonconforming Changed Work under the Base Contract's correction procedure. At completion, Contractor shall give Owner applicable warranties, test results, as-built information, lien releases, and closeout items identified here: [list].

7. No broader release

Except for the exact price and time adjustments stated above, this Change Order does not release a party's accrued claim, excuse defective work, alter insurance or indemnity obligations, change dispute procedures, or waive a nonwaivable right. A party claiming an additional change shall follow the Base Contract's written notice and authorization process.

8. Signatures

Each signer represents authority to bind the named party. The parties intend this signed record to amend the Base Contract. Counterparts and lawful electronic signatures are effective. Contractor shall attach a copy to the Base Contract records.

OWNER: ____________________ Name/title: [name and title] Date: [date]

CONTRACTOR: ____________________ Name/title: [name and title] Date: [date]

NOTICE TO PROCEED, if required: Owner authorizes the Changed Work to begin on [date].


---
License: Licensed under CC BY 4.0. Attribution is required when you publish or redistribute this Template or an adapted version to the public. Attribution is not required merely because you use or adapt the Template for your own business or legal purposes, including preparing, negotiating, signing, or exchanging an agreement with a counterparty. License details.