HOME IMPROVEMENT SERVICES AGREEMENT

California, US

Contract date: [date]

Owner: [full legal name], of [address] (Owner).

Contractor: [full legal name and entity type], business address [address], telephone [number], California contractor license number [number], classification [classification] (Contractor).

Property: Owner's existing residence at [address]. Work: the home improvement described in Schedule 1. Contract Documents: this agreement, its schedules, plans listed in Schedule 1, and signed change orders.

THE HOME IMPROVEMENT CONTRACT PRICE IS US$[TOTAL PRICE].

1. WORK AND MATERIALS

Contractor will furnish the labor, supervision, equipment and materials allocated to it in Schedule 1 and complete the Work in accordance with the Contract Documents, applicable building codes, permits and manufacturer instructions. Schedule 1 must describe each material by brand, model, quantity, color, size or other reasonably available specification and state all exclusions. No oral promise is part of this agreement.

Contractor will use appropriately licensed personnel and subcontractors. The following subcontractors will perform work exceeding US$[amount]: [name, address, license number and scope]. Contractor remains responsible for its subcontractors. [Owner / Contractor] will obtain the permits listed in Schedule 1.

2. DATES AND ACCESS

Work will start on approximately [month/day/year], but no later than [month/day/year] unless delayed by an event beyond Contractor's reasonable control. Work will be substantially completed by approximately [month/day/year]. Substantial Completion means the Work may be safely used for its intended residential purpose, subject only to a written punch list that does not materially impair use.

Owner will provide reasonable access, utilities and the information allocated in Schedule 1. Contractor will protect occupied areas, keep the site reasonably clean and remove its debris. Contractor must promptly give Owner written notice of a material delay, its cause and expected effect. An allowable delay does not increase the price without a signed change order.

3. CONTRACT PRICE; DOWN PAYMENT; SCHEDULE OF PROGRESS PAYMENTS

Owner will pay the Contract Price only as follows. The down payment is US$[amount], which may not exceed US$1,000 or 10 percent of the Contract Price, whichever is less, except where California law expressly permits otherwise.

The Schedule of Progress Payments is:

[Milestone and specific work/materials] — US$[amount].

[Milestone and specific work/materials] — US$[amount].

Substantial Completion and listed closeout items — US$[amount].

IT IS AGAINST THE LAW FOR A CONTRACTOR TO COLLECT PAYMENT FOR WORK NOT YET COMPLETED, OR FOR MATERIALS NOT YET DELIVERED. HOWEVER, A CONTRACTOR MAY REQUIRE A DOWN PAYMENT.

Each progress payment must correspond to the value of Work performed or materials delivered. Contractor will give an itemized invoice. Owner will pay an undisputed amount within [number] days after the stated milestone, any required inspection and receipt of the invoice. Owner may withhold a reasonable disputed amount after promptly stating the reason, but must pay the undisputed balance.

4. CHANGE ORDERS

Extra or changed work requires a written change order signed by Owner and Contractor before the changed work begins. Each change order must describe the change, the price increase or decrease, and its effect on the start or completion date. A change order becomes part of the Contract Documents. An oral direction does not change the price or scope. Contractor may take only reasonable temporary action needed to prevent imminent injury or property damage and must document it promptly.

Contractor may not require payment for a change before the changed work is completed, except as California law permits for a lawful progress payment tied to completed work or delivered materials.

5. INSPECTION, CORRECTION AND WARRANTY

Owner may reasonably inspect without directing Contractor's means, methods or safety. Contractor will correct Work that does not conform to the Contract Documents. Final payment is due only after Substantial Completion, required final inspections and delivery of warranties, manuals, permits and lien-related documents identified in Schedule 2.

Contractor warrants for [one year] after Substantial Completion that its Work will materially conform to the Contract Documents and be free from defects in workmanship. This warranty excludes ordinary wear, abuse, inadequate maintenance and unauthorized alteration, and does not limit any nonwaivable right.

6. INSURANCE, DAMAGE AND RESPONSIBILITY

Before starting, Contractor will provide evidence of the commercial general liability, workers' compensation and automobile coverage stated in Schedule 2. Owner will maintain property insurance for the existing residence and contents. Each party is responsible for direct loss to the extent caused by its breach, negligence or willful misconduct. Nothing requires Owner to indemnify Contractor for Contractor's own violation, negligence or willful misconduct or limits liability that cannot lawfully be limited.

7. SUSPENSION AND TERMINATION

Contractor may suspend affected Work after [seven] days' written notice if an undisputed payment remains overdue, provided the site is left safe and weather-protected. Owner may direct suspension; time and documented cost will be adjusted only by signed change order unless Contractor caused the suspension.

Either party may terminate for a material breach not cured within [seven] days after written notice, or immediately for abandonment, fraud, unlawful unlicensed performance or an imminent safety danger that cannot promptly be cured. Owner may terminate for convenience on [seven] days' written notice and pay for conforming Work performed, properly ordered nonreturnable materials and reasonable demobilization, less prior payments and direct completion costs caused by Contractor's breach. Contractor must secure the site and deliver paid-for materials and records.

8. MECHANICS LIEN WARNING

Anyone who helps improve your property, but who is not paid, may record what is called a mechanics lien on your property. A mechanics lien is a claim, like a mortgage or home equity loan, made against your property and recorded with the county recorder.

Even if you pay your contractor in full, unpaid subcontractors, suppliers, and laborers who helped to improve your property may record mechanics liens and sue you in court to foreclose the lien. If a court finds the lien valid, you could be forced to pay twice or have a court officer sell your home to pay the lien. Liens can also affect your credit.

To preserve their right to record a lien, each subcontractor and material supplier must provide you with a document called a “20-day Preliminary Notice.” This notice is not a lien. The purpose of the notice is to let you know that the person who sends you the notice has the right to record a lien on your property if he or she is not paid.

BE CAREFUL. The Preliminary Notice can be sent up to 20 days after the subcontractor starts work or the supplier provides material. This can be a big problem if you pay your contractor before you have received the Preliminary Notices.

You will not get Preliminary Notices from your prime contractor or from laborers who work on your project. The law assumes that you already know they are improving your property.

PROTECT YOURSELF FROM LIENS. You can protect yourself from liens by getting a list from your contractor of all the subcontractors and material suppliers that work on your project. Find out from your contractor when these subcontractors started work and when these suppliers delivered goods or materials. Then wait 20 days, paying attention to the Preliminary Notices you receive.

PAY WITH JOINT CHECKS. One way to protect yourself is to pay with a joint check. When your contractor tells you it is time to pay for the work of a subcontractor or supplier who has provided you with a Preliminary Notice, write a joint check payable to both the contractor and the subcontractor or material supplier.

For other ways to prevent liens, visit CSLB's website at www.cslb.ca.gov or call CSLB at 800-321-CSLB (2752).

9. INFORMATION ABOUT THE CONTRACTORS STATE LICENSE BOARD (CSLB)

CSLB is the state consumer protection agency that licenses and regulates construction contractors.

Contact CSLB for information about the licensed contractor you are considering, including information about disclosable complaints, disciplinary actions and civil judgments that are reported to CSLB.

Use only licensed contractors. If you file a complaint against a licensed contractor within the legal deadline (usually four years), CSLB has authority to investigate the complaint. If you use an unlicensed contractor, CSLB may not be able to help you resolve your complaint. Your only remedy may be in civil court, and you may be liable for damages arising out of any injuries to the unlicensed contractor or the unlicensed contractor's employees.

For more information: Visit www.cslb.ca.gov; call 800-321-CSLB (2752); or write CSLB, P.O. Box 26000, Sacramento, CA 95826.

10. GENERAL

California law governs. Notices must be written and delivered to the addresses above by [personal delivery / trackable mail / agreed email]. This agreement and its Contract Documents are the entire agreement. A waiver or amendment must be signed. Invalid language will be limited only as necessary; mandatory consumer rights remain. Counterparts and lawful electronic signatures may be used only in a manner that preserves every required copy, notice, format and cancellation right.

NOTICE TO OWNER

Under California law, the Home Improvement Contract must contain the name, address, and license number of the contractor, a description of the work to be done, when it is to be done, and the amount and timing of payments. You are entitled to a completely filled-in copy of this agreement, signed by both you and the contractor, before any work may be started.

THREE-DAY RIGHT TO CANCEL; FIVE-DAY RIGHT TO CANCEL FOR A BUYER 65 YEARS OF AGE OR OLDER

You, the buyer, have the right to cancel this contract within three business days. If you are 65 years of age or older, you have five business days to cancel. You may cancel by mailing, emailing or delivering a written notice to Contractor at [cancellation address and email] by midnight of [date]. Include your name, Property address, contract date and a statement that you cancel. Contractor must provide two completed copies of the attached Notice of Cancellation in the same language used for negotiation and must not begin work or accept prohibited payment before the cancellation period expires unless a statutory exception is fully satisfied.

Owner acknowledges receipt of the completed and signed contract and two completed Notices of Cancellation: Owner initials [ ].

SCHEDULE 1 — PROPERTY, DETAILED WORK, MATERIALS, PLANS, PERMITS, EXCLUSIONS, START AND COMPLETION DATES

[Complete all details before signing.]

SCHEDULE 2 — PAYMENT MILESTONES, INSURANCE, WARRANTY, SUBCONTRACTORS, CLOSEOUT AND NOTICE ADDRESSES

[Complete all details before signing.]

OWNER: ____________________ Name: [name] Date: [date]

CONTRACTOR: ____________________ Name/title: [name/title] License no.: [number] Date: [date]

NOTICE OF CANCELLATION

Contract date: [date]. Last date to cancel: [date].

You may cancel this transaction, without any penalty or obligation, within three business days from the above date, or within five business days if you are 65 years of age or older.

If you cancel, any property traded in, any payments made by you under the contract, and any negotiable instrument executed by you will be returned within 10 days following receipt by the seller of your cancellation notice, and any security interest arising out of the transaction will be canceled.

If you cancel, you must make available to the seller at your residence, in substantially as good condition as when received, any goods delivered to you under this contract; or you may comply with the seller's instructions regarding return shipment at the seller's expense and risk.

If you make the goods available and the seller does not pick them up within 20 days of your cancellation, you may retain or dispose of them without further obligation. If you fail to make the goods available, or agree to return them and fail to do so, you remain liable for performance of all obligations under the contract.

To cancel, mail, email or deliver a signed and dated copy of this cancellation notice, or any other written notice, to [Contractor name, address and email], no later than midnight of [date].

I HEREBY CANCEL THIS TRANSACTION.

Buyer signature: ____________________ Date: [date]

SECOND COPY OF NOTICE OF CANCELLATION

Contract date: [date]. Last date to cancel: [date].

You may cancel this transaction, without any penalty or obligation, within three business days from the above date, or within five business days if you are 65 years of age or older.

If you cancel, any property traded in, any payments made by you under the contract, and any negotiable instrument executed by you will be returned within 10 days following receipt by the seller of your cancellation notice, and any security interest arising out of the transaction will be canceled.

If you cancel, you must make available to the seller at your residence, in substantially as good condition as when received, any goods delivered to you under this contract; or you may comply with the seller's instructions regarding return shipment at the seller's expense and risk.

If you make the goods available and the seller does not pick them up within 20 days of your cancellation, you may retain or dispose of them without further obligation. If you fail to make the goods available, or agree to return them and fail to do so, you remain liable for performance of all obligations under the contract.

To cancel, mail, email or deliver a signed and dated copy of this cancellation notice, or any other written notice, to [Contractor name, address and email], no later than midnight of [date].

I HEREBY CANCEL THIS TRANSACTION.

Buyer signature: ____________________ Date: [date]



---
License: Licensed under CC BY 4.0. Attribution is required when you publish or redistribute this Template or an adapted version to the public. Attribution is not required merely because you use or adapt the Template for your own business or legal purposes, including preparing, negotiating, signing, or exchanging an agreement with a counterparty. License details.