WORKS CONTRACT
New Zealand

Date: [date].
Principal: [full legal name, constitution, NZBN/company number and address] (Principal).
Contractor: [full legal name, constitution, NZBN/company number and address] (Contractor).

Works means the discrete civil, repair, installation or improvement works described in Schedule 1 at [location] (Site). Contract Sum means NZD [amount] plus GST or the amount determined from the rates and measurements in Schedule 2. Completion Date means [date]. This Contract excludes residential building work for a household unit.

1. Carrying out the Works
The Contractor must execute and complete the Works with reasonable skill and care, using suitable labour, materials, equipment and supervision, in accordance with Schedule 1, applicable law and lawful Site requirements. It must verify dimensions reasonably capable of verification and promptly notify a discrepancy, unsafe instruction or apparent error before acting on it.

The Principal must provide access, existing-condition information, interfaces with other contractors and Principal-supplied items identified in Schedule 1. The Contractor is not responsible for an undisclosed defect in Principal information that it could not reasonably identify.

2. Approvals, health and safety
Schedule 1 must state who obtains each consent, permit, corridor or utility approval, shutdown approval, inspection and acceptance certificate. The affected work must not begin before the required approval.

Each party must comply with duties applying to it under the Health and Safety at Work Act 2015 and consult, cooperate and coordinate with other duty holders. The Contractor must maintain competent supervision, protect existing property, control its work area and make required notifications. No clause transfers a statutory duty.

3. Measurement and payment claims
For remeasurable Works, the representatives must jointly measure completed quantities and apply the Schedule 2 rates. If the Principal does not attend after reasonable notice, the Contractor may record measurements with evidence, subject to later verification.

The Contractor may serve payment claims under section 20 of the Construction Contracts Act 2002 at the intervals in Schedule 2. A claim must identify the period and Works, calculate the amount, state the due date and include the prescribed explanation. Within [10] working days, the Principal must pay or serve a complying payment schedule stating the scheduled amount and reasons for any difference. Payment is due [20] working days after service unless Schedule 2 lawfully states another date.

4. Retention money
If Schedule 2 provides for retention, subpart 2A of the Construction Contracts Act 2002 applies where its threshold and other requirements are met. The retaining party must hold retention money on trust and keep, account for, report on and pay it as required. The Contract cannot authorise contrary use.

5. Variations
Only the Principal's authorised representative may instruct a Variation. Before performance, the written instruction or agreement must state the changed scope, valuation basis, programme effect and revised Completion Date. If immediate work is reasonably needed to remove an imminent safety risk or prevent material damage, the Contractor may act and must notify the Principal promptly with cost and time records.

6. Time and access
The Contractor must start on [date], progress regularly and notify a likely delay within [three] working days after awareness. The Completion Date extends to the extent of an approved Variation, Principal default, late access or information, an undisclosed physical condition not reasonably discoverable before signing, or an unavoidable event beyond reasonable control. The affected party must mitigate.

Delay damages apply only if stated in Schedule 2, only for Contractor-caused delay and subject to the law on penalties.

7. Inspection, completion and defects
The Principal may inspect without unreasonably disrupting the Works. The Contractor must correct non-conforming work for which it is responsible and provide the tests, as-built information and operating documents required by Schedule 1.

Within [five] working days after a completion request, the Principal must issue an acceptance certificate or a reasonable defects list. The Contractor must correct notified defects attributable to its breach within a reasonable time during the [six]-month Defects Period. Acceptance does not waive latent defects, fraud or mandatory rights.

8. Risk and insurance
The Contractor bears risk in the Works until acceptance except to the extent caused by the Principal. Title to materials passes on payment or incorporation, whichever occurs first, free of undisclosed security interest. The Contractor must protect the Site and remove waste.

Before starting, the Contractor must provide evidence of the insurance in Schedule 3, including public liability and cover for the Works where stated. Insurance does not limit responsibility.

9. Suspension and termination
A party may suspend affected performance after [seven] working days' notice of an uncured material breach; immediate suspension is permitted for imminent danger. Statutory suspension rights remain available. A party may terminate for a material breach continuing [fifteen] working days after notice or insolvency, subject to mandatory law.

After termination, the Contractor must make the Site safe and deliver paid-for materials and records. The Principal must pay for conforming Works and reasonable demobilisation, less lawful set-off and reasonable cost caused by Contractor default.

10. Liability, disputes and general
Each party is liable for direct loss caused by its breach, negligence or wilful misconduct. No limitation excludes fraud, death or personal injury caused by negligence, or another non-excludable liability. Any cap is stated in Schedule 3.

Representatives must meet within [five] working days after a dispute notice. Either party may refer a dispute to adjudication under the Construction Contracts Act 2002 at any time. New Zealand law governs and its courts have jurisdiction.

The Contractor remains responsible for subcontractors. Amendments must be signed. Notices must be written and served consistently with statutory requirements. Counterparts and electronic signatures may be used where the Contract and Commercial Law Act 2017 permits.

SCHEDULE 1 — WORKS AND SITE
Site, existing conditions and access: [details].
Scope, drawings, specifications and exclusions: [details].
Principal inputs and interfaces: [details].
Consents, inspections and responsible party: [details].
Tests, deliverables and acceptance criteria: [details].
Start date, programme and Completion Date: [details].

SCHEDULE 2 — PRICE, MEASUREMENT AND CLAIMS
Lump sum or rates and quantities: [details].
Claim intervals, calculation and evidence: [details].
Payment-schedule period and due date: [details].
Retention and release: [details or none].
Delay damages, if agreed: [details].

SCHEDULE 3 — INSURANCE, LIABILITY AND CONTACTS
Policies, limits and period: [details].
Liability cap, if agreed: [details].
Authorised representatives and notices: [details].

SIGNATURES
For the Principal: [authorised signatory, position, signature and date].
For the Contractor: [authorised signatory, position, signature and date].



---
License: Licensed under CC BY 4.0. Attribution is required when you publish or redistribute this Template or an adapted version to the public. Attribution is not required merely because you use or adapt the Template for your own business or legal purposes, including preparing, negotiating, signing, or exchanging an agreement with a counterparty. License details.