# TURNKEY CONTRACT

*New Zealand*

Date: [date].

Purchaser: [full legal name, constitution, NZBN/company number and address] (Purchaser).

Turnkey Contractor: [full legal name, constitution, NZBN/company number and address] (Contractor).

The Asset is [facility/system] to be delivered ready for safe intended use at [address] (Site). The Turnkey Works are all design, procurement, construction, installation, commissioning, training and handover obligations in Schedule 1. Turnkey Price means NZD [amount] plus GST, adjusted only under this Contract. Required Handover Date means [date]. Handover has the meaning in clause 8. Variation means a change authorised under clause 6. Working Day has the meaning given in the Construction Contracts Act 2002.

## 1. Turnkey result

The Contractor must deliver the complete Asset so that it is safe, operable and capable of the functions, output and performance stated in Schedule 1. Except for Purchaser items and exclusions expressly listed there, the Turnkey Price includes everything reasonably necessary for that result, including interfaces, commissioning consumables, temporary works, initial spares, manuals and training.

The Contractor must perform with reasonable skill and care, comply with the consented documents, the New Zealand Building Code and other applicable law, and coordinate its designers, vendors and subcontractors. It must promptly warn of an error, ambiguity, unsafe requirement or missing interface that a competent turnkey contractor should identify. It may rely only on Purchaser information expressly identified in Schedule 1.

## 2. Purchaser inputs, consents and review

The Purchaser must provide lawful Site access, authority to install and operate the Asset, Purchaser utilities, inputs and decisions by the dates in Schedule 1. Schedule 1 must allocate building consent, resource consent, utility approvals, inspections, code compliance certification and operating approvals. The responsible party must obtain an approval before the affected activity.

A Purchaser review or attendance at a test does not transfer the Contractor's responsibility, approve a deviation or amend this Contract. Each party remains responsible for duties imposed on it by law.

## 3. Safety and Site control

The Contractor controls its methods, personnel and work areas and must maintain competent supervision, a quality plan, inspection records and protection of the Site and adjoining property. Each party must comply with duties under the Health and Safety at Work Act 2015 and consult, co-operate and co-ordinate with other duty holders. No term transfers or limits a statutory duty.

The Contractor remains responsible for subcontractors and suppliers and may not subcontract the whole Turnkey Works without consent.

## 4. Payment claims and retentions

The Contractor may serve payment claims under section 20 of the Construction Contracts Act 2002 at the milestones in Schedule 2. Each claim must identify the relevant period and Turnkey Works, calculate the claimed amount, state the due date and include the prescribed explanation.

Within [10] Working Days after service, the Purchaser must pay the claimed amount or serve a payment schedule complying with section 21 that states the scheduled amount and reasons for each difference. Payment is due [20] Working Days after service unless Schedule 2 lawfully states another date. Statutory debt, suspension and adjudication rights remain available.

Any retention must be stated in Schedule 2. Where subpart 2A of the Construction Contracts Act 2002 applies, retention money is trust money and the retaining party must keep, use, account for, report on and pay it only as that Act permits. Release conditions cannot override mandatory law.

## 5. Design, procurement and documents

The Contractor must prepare and control the drawings, calculations, specifications, software configurations, quality records and vendor documents in Schedule 1. It must procure new and conforming equipment unless Schedule 1 states otherwise, conduct required inspections and provide title free of undisclosed security interests. Title passes on payment or delivery to the Site, whichever occurs first, while risk remains with the Contractor until Handover except to the extent caused by the Purchaser.

The Contractor retains intellectual property in its documents but grants the Purchaser a perpetual, royalty-free, transferable licence to use and adapt them to operate, maintain, repair and alter the Asset. It must have authority to grant that licence.

## 6. Variations and Site conditions

A Variation must be in writing and state the changed output or work, valuation method, programme effect, performance effect and revised Required Handover Date. If price is not agreed before work proceeds, it is determined using Schedule 2 rates or, if none, reasonable verified cost plus [percentage]% overhead and profit. Urgent protective work may proceed with prompt notice and records.

If the Contractor encounters a physical condition materially different from reliable Site information in Schedule 1 and not reasonably discoverable before signing, it must protect the work and notify the Purchaser before disturbing the condition. Any adjustment follows the Variation process.

## 7. Programme and delay

The Contractor must maintain a programme covering design, manufacture, transport, installation, commissioning, training and Handover. It must notify a delaying event within [three] Working Days after awareness and provide particulars and mitigation within [seven] further Working Days.

The Required Handover Date extends to the extent delay results from an approved Variation, Purchaser default, late access or input, a qualifying Site condition, or an unavoidable event beyond reasonable control despite mitigation. Delay damages in Schedule 2 apply only to Contractor-caused delay after that date, at the stated daily amount and cap, subject to the law on penalties.

## 8. Commissioning and Handover

The Contractor must commission the Asset and perform the reliability and performance tests in Schedule 1 with reasonable notice. Handover occurs when the Asset passes those tests, is ready for safe intended use, required Contractor approvals have been obtained, operators have received agreed training, and essential manuals, spares, warranties and as-built records are delivered.

Within [five] Working Days after a Handover request, the Purchaser must issue a Handover Certificate or a reasonable list of material failures. Minor items not preventing safe intended use may be listed for prompt completion. A result below a guaranteed value but at or above the minimum acceptance level may be accepted only with the adjustment in Schedule 2. A result below the minimum level requires correction or a signed Variation.

The Contractor must correct notified defects caused by its breach within a reasonable time during the [twelve]-month Warranty Period. Handover, operation or final payment does not waive latent defects, fraud or mandatory rights.

## 9. Insurance, suspension and termination

Before starting, the Contractor must provide evidence of the transit, contract works, public liability, professional indemnity and other insurance in Schedule 3. Insurance does not limit responsibility.

A party may suspend affected performance after [seven] Working Days' notice of an uncured material breach; immediate suspension is permitted for imminent safety risk. Statutory suspension rights remain available. A party may terminate for a material breach remaining uncured [fifteen] Working Days after notice or insolvency, subject to mandatory law. On termination, the Contractor must make the Site safe and hand over paid-for equipment, work and records. The Purchaser must pay for conforming work and reasonable demobilisation, less lawful set-off and reasonable completion cost caused by Contractor default.

## 10. Liability, disputes and general

Each party is liable for direct loss caused by breach, negligence or wilful misconduct. No limitation excludes fraud, death or personal injury caused by negligence, unpaid amounts or liability that cannot lawfully be limited. Any cap is stated in Schedule 3.

Representatives must meet within [five] Working Days after a dispute notice. Either party may refer a dispute to adjudication under the Construction Contracts Act 2002 at any time. Other statutory or court remedies remain available. New Zealand law governs and its courts have jurisdiction.

Amendments must be signed. Notices must be written and served consistently with statutory requirements and Schedule 3. Counterparts and electronic signatures may be used where the Contract and Commercial Law Act 2017 permits.

## SCHEDULE 1 — ASSET AND TURNKEY REQUIREMENTS

Site, Asset, intended use, interfaces and exclusions: [details].

Output, capacity, efficiency and guaranteed performance: [details].

Minimum acceptance levels and test methods: [details].

Purchaser inputs, utilities and reliance items: [details].

Programme and Required Handover Date: [details].

Consents, inspections and responsible party: [details].

Training, manuals, spares, warranties and handover records: [details].

## SCHEDULE 2 — PRICE, CLAIMS AND ADJUSTMENTS

Turnkey Price and GST: [details].

Claim milestones, calculations and evidence: [details].

Payment-schedule period and due date: [details].

Advances, retentions and securities: [details or none].

Variation rates and overhead/profit percentage: [details].

Delay damages and performance adjustments: [details].

## SCHEDULE 3 — INSURANCE, LIABILITY AND CONTACTS

Policies, limits and periods: [details].

Liability cap, if agreed: [details].

Authorised representatives and notices: [details].

## SIGNATURES

For the Purchaser: [authorised signatory, position, signature and date].

For the Contractor: [authorised signatory, position, signature and date].


---
License: Licensed under CC BY 4.0. Attribution is required when you publish or redistribute this Template or an adapted version to the public. Attribution is not required merely because you use or adapt the Template for your own business or legal purposes, including preparing, negotiating, signing, or exchanging an agreement with a counterparty. License details.