CONSTRUCTION CONTRACT
New Zealand

Date: [date].
Principal: [full legal name, constitution, NZBN/company number and address] (Principal).
Contractor: [full legal name, constitution, NZBN/company number and address] (Contractor).

Works means the commercial construction work described in Schedule 1 at [site address] (Site). Contract Price means NZD [amount] plus GST, subject only to approved Variations. Completion Date means [date]. This template is not for a residential consumer build.

1. Works and dependencies
The Contractor must carry out and complete the Works with reasonable skill and care, in accordance with Schedule 1, approved drawings, lawful directions and applicable law. It must provide labour, materials, supervision and equipment allocated to it in Schedule 1 and may not materially depart from the design without an approved Variation.

The Principal must provide lawful Site access, information and Principal-supplied items by the dates in Schedule 1. Neither party is responsible for delay caused solely by the other's failure to perform a stated dependency.

2. Consents, safety and insurance
Schedule 1 must allocate responsibility for each building consent, resource consent, inspection, utility approval and code compliance certificate. The responsible party must obtain it before affected work starts.

Each party must comply with duties that apply to it under the Health and Safety at Work Act 2015 and must consult, cooperate and coordinate with other duty holders. No clause transfers or limits a statutory duty. Before starting, the Contractor must provide evidence of the insurance in Schedule 3, including contract works and public liability cover where required.

3. Payment claims and schedules
The Contractor may issue payment claims at the milestones in Schedule 2. Each claim must meet section 20 of the Construction Contracts Act 2002, identify the relevant period and work, show the claimed amount and calculation, state the due date, and include the prescribed explanation of responding and consequences.

The Principal must, within [10] working days after service, pay the claimed amount or serve a payment schedule complying with section 21 that states the scheduled amount and explains every difference. Payment is due [20] working days after the claim unless Schedule 2 lawfully states another date. The Act's consequences for failing to schedule or pay, suspension rights and adjudication rights apply and cannot be contracted out of.

4. Retention money
Any retention must be expressly stated in Schedule 2. To the extent subpart 2A of the Construction Contracts Act 2002 applies, retention money is trust money and the retaining party must keep, use, account for, report on and pay it as that Act requires. No clause permits commingling, use or withholding contrary to the Act. If the statutory subpart does not apply, Schedule 2 still governs release.

5. Variations
A Variation is effective only if a written instruction or agreement identifies the change, valuation method, programme effect and revised Completion Date. If urgent work is reasonably needed to prevent imminent injury or property damage, the Contractor may act first but must notify the Principal promptly and keep cost records.

6. Time and delay
The Contractor must notify a likely delay within [three] working days after becoming aware of it, stating cause, effect and mitigation. The Completion Date extends only to the extent delay is caused by an approved Variation, Principal default, an undisclosed physical condition not reasonably discoverable before signing, or an event beyond the affected party's reasonable control that it could not avoid. The Contractor must mitigate.

If agreed, delay damages are NZD [amount] per working day capped at [percentage]% of the Contract Price and apply only to Contractor-caused delay after the Completion Date. A court may refuse an unenforceable penalty.

7. Completion and defects
The Contractor must notify when the Works are ready for inspection. The Principal must within [five] working days issue a completion certificate or a reasonable defects list. Minor defects not preventing intended use do not justify refusal. The Contractor must correct notified defects attributable to its breach within a reasonable time during the [twelve]-month Defects Period. This does not limit a mandatory remedy or latent-defect claim.

8. Title, risk and Site care
Title to materials passes on the earlier of payment or incorporation into the Works, free of undisclosed security interest. The Contractor bears risk in the Works until completion except to the extent caused by the Principal. The Contractor must protect the Site, minimise nuisance and remove waste.

9. Suspension and termination
A party may suspend affected performance after [seven] working days' written notice of an uncured material breach, except immediate suspension is permitted for imminent safety risk. Statutory suspension under the Construction Contracts Act 2002 remains available.

A party may terminate if a material breach remains uncured [fifteen] working days after notice or the other enters insolvency, subject to mandatory law. On termination, the Contractor must secure the Site and hand over paid-for work, materials and records. The Principal must pay for conforming work and reasonable demobilisation, less lawful set-off and completion cost caused by Contractor default.

10. Liability and disputes
Each party is liable for direct loss caused by its breach, negligence or wilful misconduct. Neither excludes liability for fraud, death or personal injury caused by negligence, or liability that cannot lawfully be limited. Total liability is capped at [percentage]% of the Contract Price except for those matters, unpaid amounts, third-party property damage and infringement caused by supplied design.

Senior representatives must meet within [five] working days of a dispute notice. Either party may refer a dispute to adjudication under the Construction Contracts Act 2002 at any time; other proceedings and statutory enforcement rights remain available. New Zealand law governs and its courts have jurisdiction.

11. General
The Contractor may not subcontract the whole Works and remains responsible for subcontractors. Changes other than Variations must be signed. Notices must be written and delivered by hand, tracked post or email, subject to statutory service rules. Counterparts and electronic signatures may be used where the Contract and Commercial Law Act 2017 permits.

SCHEDULE 1 — WORKS AND SITE
Site, scope, drawings, specifications and exclusions: [details].
Programme, Completion Date and dependencies: [details].
Principal-supplied information/items: [details].
Consents and responsible party: [details].
Testing and acceptance criteria: [details].

SCHEDULE 2 — PRICE, CLAIMS AND RETENTIONS
Contract Price and GST: [details].
Claim milestones, amounts and evidence: [details].
Payment schedule response period and due date: [details].
Retention percentage, statutory status and release: [details or none].
Delay damages, if agreed: [details].

SCHEDULE 3 — INSURANCE AND CONTACTS
Required policies, limits and period: [details].
Authorised representatives and notice details: [details].

SIGNATURES
For the Principal: [authorised signatory, position, signature and date].
For the Contractor: [authorised signatory, position, signature and date].



---
License: Licensed under CC BY 4.0. Attribution is required when you publish or redistribute this Template or an adapted version to the public. Attribution is not required merely because you use or adapt the Template for your own business or legal purposes, including preparing, negotiating, signing, or exchanging an agreement with a counterparty. License details.