WORKS CONTRACT
India

Date: [date].
Employer: [full legal name, constitution, registration number and address] (Employer).
Contractor: [full legal name, constitution, registration number and address] (Contractor).

Works means the discrete civil, repair, installation or improvement works described in Schedule 1 at [location] (Site), excluding the sale or development of land. Contract Sum means INR [amount] or the amount determined from the rates and measurements in Schedule 2. Completion Date means [date].

1. Performance of the Works
The Contractor must execute and complete the Works with reasonable skill and care, using suitable labour, materials, equipment and supervision, in accordance with Schedule 1, applicable law and lawful Site requirements. The Contractor must verify dimensions reasonably capable of verification and promptly notify a discrepancy or unsafe instruction before acting on it.

The Employer must provide access, existing-condition information, interfaces with other contractors and Employer-supplied items identified in Schedule 1. The Contractor is not responsible for an Employer design defect that it could not reasonably identify before performance.

2. Permits, personnel and safety
Schedule 1 must state who obtains each permit, shutdown approval, utility clearance, inspection and acceptance certificate. No affected work may begin before the required approval is in place.

The Contractor must comply with applicable worker-registration, wage, welfare, safety and environmental requirements, maintain required Site records and ensure competent supervision. The parties retain all duties imposed directly on them by law, including principal-employer duties where applicable.

3. Measurement, invoices and payment
For lump-sum work, payment follows the milestones in Schedule 2. For remeasurable work, the parties' representatives must jointly measure completed quantities and apply the agreed rates; if the Employer does not attend after reasonable notice, the Contractor may record measurements with supporting evidence subject to later verification.

Each invoice must show completed Works, measurements, approved Variations, GST and statutory deductions. Within [seven] Business Days, the Employer must pay the undisputed amount or give reasons for each disputed amount. GST, tax deduction at source and other statutory charges must be treated as law requires. Eligible micro or small enterprise rights are not waived.

4. Variations
Only the Employer's authorised representative may instruct a Variation. Before performing it, the parties must sign a document stating the changed scope, valuation, time effect and any revised Completion Date. If immediate work is reasonably needed to remove an imminent safety risk or prevent material damage, the Contractor may act and must notify the Employer promptly with cost and time records.

5. Time and access
The Contractor must start on [date], progress regularly and notify a likely delay within [three] Business Days after awareness. The Completion Date extends to the extent delay results from an approved Variation, late access or information from the Employer, an undisclosed physical condition not reasonably discoverable before signing, or an unavoidable event beyond reasonable control. The affected party must mitigate.

Delay damages apply only if completed in Schedule 2, only for Contractor-caused delay, and only to the extent enforceable rather than penal.

6. Inspection, acceptance and defects
The Employer may inspect without unreasonably disrupting the Works. The Contractor must correct non-conforming work for which it is responsible. On completion, the Contractor must provide test results, as-built information and operating documents required by Schedule 1 and request acceptance.

Within [five] Business Days, the Employer must issue an acceptance certificate or a reasonable defects list. The Contractor must correct notified defects attributable to its breach during the [six]-month Defects Period within a reasonable time. Acceptance does not waive latent defects, fraud or mandatory rights.

7. Care of the Works and insurance
The Contractor bears risk of loss to the Works until acceptance except to the extent caused by the Employer. Title to materials passes on payment or incorporation, whichever occurs first, free of undisclosed charge. The Contractor must protect existing property and remove waste.

Before starting, the Contractor must provide evidence of the insurance in Schedule 3, including third-party liability and cover for the Works where specified. Insurance does not limit responsibility.

8. Suspension and termination
A party may suspend affected performance after [seven] Business Days' notice of an uncured material breach; immediate suspension is permitted for imminent danger. A party may terminate for a material breach continuing [fifteen] Business Days after notice or insolvency, subject to mandatory law.

After termination, the Contractor must make the Site safe and deliver paid-for materials and records. The Employer must pay for conforming Works performed, verified materials and reasonable demobilisation, less lawful set-off and reasonable cost caused by Contractor default.

9. Liability and dispute resolution
Each party is liable for direct loss caused by its breach, negligence or wilful misconduct. No limitation excludes fraud, death or personal injury caused by negligence, or another non-excludable liability. The cap, if any, is stated in Schedule 3.

Representatives must meet within [five] Business Days after a dispute notice. If unresolved within [ten] further Business Days, either party may bring proceedings. Indian law governs and, subject to mandatory jurisdiction rules, courts at [city, State/Union Territory] have exclusive jurisdiction.

10. General
The Contractor remains responsible for subcontractors. Neither party may assign this Contract without written consent, not to be unreasonably withheld where the assignee can perform. Amendments must be signed. Notices must be written and delivered by hand, tracked post or email, effective on proven receipt. Counterparts and valid electronic signatures may be used. Applicable State or Union Territory stamp-duty and execution requirements must be completed.

SCHEDULE 1 — WORKS AND SITE
Site, existing conditions and access: [details].
Scope, drawings, specifications and exclusions: [details].
Employer-supplied information/items and interfaces: [details].
Permits, inspections and responsible party: [details].
Tests, deliverables and acceptance criteria: [details].
Start date, programme and Completion Date: [details].

SCHEDULE 2 — PRICE, MEASUREMENT AND PAYMENT
Lump sum or rates and quantities: [details].
GST, TDS, milestones and evidence: [details].
Retention and release, if any: [details].
Delay damages, if agreed: [details].

SCHEDULE 3 — INSURANCE, LIABILITY AND CONTACTS
Policies, limits and period: [details].
Liability cap, if agreed: [details].
Authorised representatives and notices: [details].

SIGNATURES
For the Employer: [authorised signatory, position, signature and date].
For the Contractor: [authorised signatory, position, signature and date].



---
License: Licensed under CC BY 4.0. Attribution is required when you publish or redistribute this Template or an adapted version to the public. Attribution is not required merely because you use or adapt the Template for your own business or legal purposes, including preparing, negotiating, signing, or exchanging an agreement with a counterparty. License details.